After the high pressure pump is in place and all fittings and high pressure tubes are installed, the high pressure pump is ready for debugging and testing operation.

Debugging and Testing

Debugging and Testing

notice sign

Check the environment around the equipment and make sure it is clean. Clean all the tools in this area and then prepare to start the equipment.

Power supply

Electricity needs to conform to the requirements of the "power requirement".
Open all the external power supply breakers. Then use a multi meter to measure the power supply voltage before turn on the power.
Turn on the main power switch on the ultra-high pressure pump. The oil temperature digital display should show the oil temperature at this moment.
Release the E-stop button and the equipment power indicator should light up.
Turn on and off the oil pump to see the rotation direction of the motor. The motor shaft rotation direction should be same as the arrow on oil pump. For related operation procedure, please refer to "Operation".
Turn off the power supply. Tighten all wiring of electrical box with the tools.

warning flash

Cable connection and change of phase sequence should be done by professionals. All-Powerful company is not responsible for the completion of this work.

Cutting Water and Cooling Water

Operate the machine strictly according to "water requirements". Water quality must meet the required standards.
Input cutting water quality is one of the important factors that affect the service life of the components and properties. Impurities in water would lead to wear and corrosion of all the parts.
Cooling water needs to be filtered. Softened cooling water can prolong the service life of heat exchanger and increase the cooling effect.
Before shut off all manual valves, put the inlet pipe off the intensifier.
Open cooling water valve, making the cooling water circuit smoothly. Check whether the flow of cooling water meets the requirements of the equipment.

notice sign

When the oil/water heat exchanger (cooler) started to run, the water releases from the cooling water drain may not be clean. And it cannot be recycled. It should be released through sewer.

Open the cutting water inlet valve a little. Therefore, make sure the water flow is small in order to release the air in the filter.
The ultra-high pressure pump equipped with a water filter. Release the air in filter by pressing the red button on top of the filter.
Fully open the cutting water inlet valve. Make the water flowing out from the intensifier inlet pipe for ten to fifteen minutes until the impurities and air in the feed line are all released.
Turn on the water booster pump. The water flow rate of the intensifier inlet pipe will increase; Wait for five minutes and connect the intensifier inlet pipe back. Operation of low pressure water should refer to "Operation".

notice sign

All low-pressure water inlets should be installed with manual shut-off valve by the user. Ultra-high pressure pump has no low pressure inlet water shut-off valve.

notice sign

If cut water and cooling water use the same water recycling source, the user should make sure that the cooling water circuit should not be polluted.

notice sign

If there is softened water equipment in the system, clean it first. Ensure that it won't pollute the water.